The UK Government has committed to achieving net zero carbon emissions by the year 2050. This has had a snowball effect on local government, with many councils committing to this same target by 2030. Southampton City Council is no exception.
In 2016, the council set out a Clean Air Strategy to run until 2025 – at which point another strategy will be produced. As part of this, the council has been meticulous in creating a clean air zone. Converting its fleet to electric vehicles and providing charging infrastructure for local residents and visitors to the area has been a key part of this plan. Joju has assisted Southampton with the installation of over 30 charge points across a number of council owned buildings and depots. However, it’s not just about volume. It’s important to install the right charger in the right place to operate a functional electric fleet.
While the council largely installed AC fast charge points for small vans and fleet cars to charge overnight, they also wanted the ability to charge vehicles quickly, within an hour, at a ‘stop and go’ site. The council was cautious about installing a 50kW rapid charge point due to the size constraints of the allocated site and the available capacity on the existing supply within the building. Joju was able to provide a solution that was cheaper than a 50kW rapid charger, had the ability to recharge vehicles onsite within an hour and one that adhered to the dimensions and size constraints of the site.
The ABB 25kW DC Wallbox was installed using the existing supply in the building and on the wall of the building. This charge point has the capacity to recharge a battery from 20% to 80% (depending on battery size) within an hour, using either a CCS or CHAdeMO connector.
We were able to orchestrate the project for the council from the design phase, through surveying, installation and commissioning, and ongoing maintenance post-installation.
The council has ambitious targets to electrify its entire fleet of vehicles before 2030 and we hope to continue our longstanding relationship, helping the council to realise and achieve these goals.
There are ongoing fleet installations, and the council is currently looking at the demonstration of electric refuse collection vehicles. Further to this, the council is hoping to increase the provision of publicly accessible charging infrastructure throughout surface car parks.
Discover more about our Public Sector EV approach
Read other Public EV Charging case studies
Hear Dr Chris Jardine share his thoughts on UK EV Infrastructure
July 13, 2021
ABB, EV Charging, Public EV